An enormous 50 tonne crane is currently on site to help lift 35 tonnes worth of structural steel into place for our new Clubhouse. We expect the exterior framing to be finished by early March so the trusses and roof can then be installed. To give you an idea of this building’s sheer size, it will take approximately three weeks to finish the roof. An average-sized home usually takes just three days!

A whopping 64 truckloads of concrete were brought onto site to pour the 1500m² foundation pad earlier this month. The Clubhouse should be weather-tight by June and will eventually be clad in Hinuera stone and cedar to match our beautiful homes.

The surrounding carpark and roads are also being prepped and should be sealed within a month. Meanwhile, consent for the adjacent health spa (which will house our swimming pool, sauna and gymnasium), has been submitted to council and we expect to get the go-ahead in March so construction can begin. We’re all looking forward to watching these fantastic facilities be built.